Dept. of Trans. PROGRESS Serial No. Contract No. 18-264-11-10 04-4J3404 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 61% Location: Federal Project: 04-CC-80-0.0/10.1 ACIM-080-1(117) Progress payment No. 013 Payment period ending: 09-20-18 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,997,475.35 2,401,356.00 2. a. Extra Work 427,523.13 4,213.38 b. Adustment Comp. 619,115.35 113,271.40 3. Materials on Hand 106,268.69 0.00 4. Earned Subject to Retention 18,150,382.52 2,518,840.78 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 20,044,113.83 7. Deductions -12,900.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,137,482.52 2,518,840.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,518,840.78