Dept. of Trans. PROGRESS Serial No. Contract No. 22-258-16-38 04-4J4204 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 22% Location: Federal Project: 04-MRN-101-0.2 STER-27F5(1) Progress payment No. 006 Payment period ending: 09-20-22 MAGGIORA & GHILOTTI INC 555 DUBOIS ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 426,256.50 87,129.75 2. a. Extra Work 54,890.13 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 481,146.63 87,129.75 5. Mobilization 70,929.00 0.00 6. Total Work Completed 552,075.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 552,075.63 87,129.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,129.75