Dept. of Trans. PROGRESS Serial No. Contract No. 22-353-16-54 04-4J4204 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 38% Location: Federal Project: 04-MRN-101-0.2 STER-27F5(1) Progress payment No. 009 Payment period ending: 12-20-22 MAGGIORA & GHILOTTI INC 555 DUBOIS ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 639,892.50 30,346.00 2. a. Extra Work 96,598.37 13,438.24 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 736,490.87 43,784.24 5. Mobilization 70,929.00 0.00 6. Total Work Completed 807,419.87 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 807,419.87 43,784.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,784.24