Dept. of Trans. PROGRESS Serial No. Contract No. 24-323-14-52 04-4J5404 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 83% Location: Federal Project: 04-ALA-880-27.0/27.4 ACIM-8801(988) Progress payment No. 005 Payment period ending: 11-20-24 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,420,149.20 787,491.85 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,420,149.20 787,491.85 5. Mobilization 284,050.00 0.00 6. Total Work Completed 1,704,199.20 7. Deductions -196,872.96 -196,872.96 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,507,326.24 590,618.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 590,618.89