Dept. of Trans. PROGRESS Serial No. Contract No. 18-081-10-50 04-4J5604 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 71% Location: Federal Project: 04-SM-1-R43.7/R46.5 NONE 04-SM-101-0.9/R20.7 04-SM-280-R1.6/M27.4 Progress payment No. 007 Payment period ending: 03-20-18 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 485,050.87 26,251.47 2. a. Extra Work 27,909.20 27,909.20 b. Adustment Comp. 10,000.00 10,000.00 3. Materials on Hand 4. Earned Subject to Retention 522,960.07 64,160.67 5. Mobilization 92,848.25 0.00 6. Total Work Completed 615,808.32 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 615,808.32 64,160.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 64,160.67