Dept. of Trans. PROGRESS Serial No. Contract No. 17-264-14-23 04-4J5804 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 13% Location: Federal Project: 04-SCL-17-0.1/1.0 NONE 04-SCL-101-0.1/1.0 04-SCL-237-0.1/1.0 Progress payment No. 001 Payment period ending: 09-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 247,162.10 247,162.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 247,162.10 247,162.10 5. Mobilization 105,000.00 105,000.00 6. Total Work Completed 352,162.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 352,162.10 352,162.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 352,162.10