Dept. of Trans. PROGRESS Serial No. Contract No. 21-168-11-38 04-4J7304 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 38% Location: Federal Project: 04-ALA-880-20.9/20.9 HSIM-8801(911) Progress payment No. 003 Payment period ending: 06-20-21 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 687,050.05 291,184.83 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 24,544.17 24,544.17 4. Earned Subject to Retention 711,594.22 315,729.00 5. Mobilization 234,650.00 49,400.00 6. Total Work Completed 921,700.05 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 946,244.22 365,129.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 365,129.00