Dept. of Trans. PROGRESS Serial No. Contract No. 21-203-11-46 04-4J7304 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 50% Location: Federal Project: 04-ALA-880-20.9/20.9 HSIM-8801(911) Progress payment No. 004 Payment period ending: 07-20-21 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 727,797.72 40,747.68 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 49,088.34 24,544.17 4. Earned Subject to Retention 776,886.06 65,291.85 5. Mobilization 234,650.00 0.00 6. Total Work Completed 962,447.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,011,536.06 65,291.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 65,291.85