Dept. of Trans. PROGRESS Serial No. Contract No. 23-229-08-34 04-4J8704 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 46% Location: Federal Project: 04-SM-1-14.0/14.0 NONE Progress payment No. 003 Payment period ending: 08-20-23 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 674,674.00 113,950.00 2. a. Extra Work 13,477.96 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 688,151.96 113,950.00 5. Mobilization 236,550.00 0.00 6. Total Work Completed 924,701.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 924,701.96 113,950.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 113,950.00