Dept. of Trans. PROGRESS Serial No. Contract No. 24-109-18-30 04-4J9104 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 26% Location: Federal Project: 04-SCL-87-0.0/6.1 ACNH-P087(34) Progress payment No. 009 Payment period ending: 04-20-24 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,424,162.82 2,788,018.60 2. a. Extra Work 697,313.62 13,200.00 b. Adustment Comp. 64,947.56 0.00 3. Materials on Hand 553,288.54 0.00 4. Earned Subject to Retention 27,739,712.54 2,801,218.60 5. Mobilization 4,250,000.00 212,500.00 6. Total Work Completed 31,436,424.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,989,712.54 3,013,718.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,013,718.60