Dept. of Trans. PROGRESS Serial No. Contract No. 23-019-12-04 04-4J9704 PROGRESS PAYMENT VOUCHER %complete: %time: 5% 25% Location: Federal Project: 04-SF-101-0.5/M5.2 ACNH-X075(49) 04-SF-280-R2.5/T7.3 Progress payment No. 003 Payment period ending: 01-20-23 HOSELEY CORPORATION PO BOX 881386 SAN FRANCISCO CA 94188 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 80,500.00 4,000.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 243,148.79 93,148.79 4. Earned Subject to Retention 323,648.79 97,148.79 5. Mobilization 275,000.00 275,000.00 6. Total Work Completed 355,500.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 598,648.79 372,148.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 372,148.79