Dept. of Trans. PROGRESS Serial No. Contract No. 19-130-10-18 04-4K2404 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 70% Location: Federal Project: 04-MRN-1-10.9/10.9 NONE Progress payment No. 040 Payment period ending: 04-10-19 DRILL TECH DRILLING & SHORING INC 2200 WYMORE WAY ANTIOCH CA 94509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 14,540,944.94 412,860.37 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 14,540,944.94 412,860.37 5. Mobilization 6. Total Work Completed 14,540,944.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,540,944.94 412,860.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 412,860.37