Dept. of Trans. FINAL Serial No. Contract No. 17-303-11-55 04-4K3204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SM-101-3.5/12.6 NONE Progress payment No. 003 Payment period ending: 06-20-17 O'GRADY PAVING INC 2513 WYANDOTTE ST MOUNTAIN VIEW CA 94043 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,360.00 0.00 2. a. Extra Work 655,546.16 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 658,906.16 0.00 5. Mobilization 6. Total Work Completed 658,906.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 658,906.16 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00