Dept. of Trans. PROGRESS Serial No. Contract No. 17-297-09-38 04-4K4504 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 44% Location: Federal Project: 04-SON-101-37.1/37.2 NONE Progress payment No. 003 Payment period ending: 10-20-17 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 525,733.74 181,411.14 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 525,733.74 181,411.14 5. Mobilization 6. Total Work Completed 525,733.74 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 525,733.74 181,411.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 181,411.14