Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-340-12-54 04-4K6204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SCL-152-7.9/9.4 NONE Progress payment No. 004 Payment period ending: 09-08-17 QA CONSTRUCTORS INC 19060 LAUREL DRIVE LOS GATOS CA 95033 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,550.00 11,550.00 2. a. Extra Work 739,869.94 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 751,419.94 11,550.00 5. Mobilization 6. Total Work Completed 751,419.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 751,419.94 11,550.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,550.00