Dept. of Trans. PROGRESS Serial No. Contract No. 17-284-12-44 04-4K7604 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 100% Location: Federal Project: 04-ALA-84-22.2/22.5 NONE Progress payment No. 004 Payment period ending: 10-11-17 R J GORDON CONSTRUCTION INC PO BOX 23204 PLEASANT HILL CA 94523 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 858,232.89 160,726.71 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 858,232.89 160,726.71 5. Mobilization 6. Total Work Completed 858,232.89 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 858,232.89 160,726.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 160,726.71