Dept. of Trans. PROGRESS Serial No. Contract No. 17-226-09-11 04-4K8004 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 19% Location: Federal Project: 04-SCL-35-10.5/10.5 NONE Progress payment No. 002 Payment period ending: 07-07-17 DISNEY CONSTRUCTION INC 859 COWAN RD #3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 377,077.20 320,921.24 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 377,077.20 320,921.24 5. Mobilization 6. Total Work Completed 377,077.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 377,077.20 320,921.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 320,921.24