Dept. of Trans. PROGRESS Serial No. Contract No. 17-292-14-28 04-4K9204 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 100% Location: Federal Project: 04-ALA-580-36.8/38.5 NONE Progress payment No. 001 Payment period ending: 10-19-17 REDGWICK CONSTRUCTION CO. 21 HEGENBERGER CT OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 209,470.75 209,470.75 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 209,470.75 209,470.75 5. Mobilization 6. Total Work Completed 209,470.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 209,470.75 209,470.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 209,470.75