Dept. of Trans. PROGRESS Serial No. Contract No. 17-338-11-04 04-4K9604 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 100% Location: Federal Project: 04-SON-116-39.9/40.1 NONE Progress payment No. 002 Payment period ending: 11-30-17 PIAZZA CONSTRUCTION PO BOX 573 PENNGROVE CA 94951 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 385,482.71 175,946.11 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 385,482.71 175,946.11 5. Mobilization 6. Total Work Completed 385,482.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 385,482.71 175,946.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 175,946.11