Dept. of Trans. PROGRESS Serial No. Contract No. 19-330-09-39 04-4Q2604 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 13% Location: Federal Project: 04-ALA-84-21.9/21.9 NONE Progress payment No. 003 Payment period ending: 11-26-19 REDGWICK CONSTRUCTION CO. 21 HEGENBERGER CT OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 262,690.06 125,399.32 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 262,690.06 125,399.32 5. Mobilization 6. Total Work Completed 262,690.06 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 262,690.06 125,399.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 125,399.32