Dept. of Trans. PROGRESS Serial No. Contract No. 19-262-17-02 04-4Q4004 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 98% Location: Federal Project: 04-NAP-128-9.2/9.2 NONE Progress payment No. 003 Payment period ending: 09-20-19 TEAM GHILOTTI INC ATTN: JOE MOREIRA, PRJ MGR 2531 PETALUMA BLVD SOUTH PETALUMA CA 94952 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 372,471.54 126,005.66 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 372,471.54 126,005.66 5. Mobilization 6. Total Work Completed 372,471.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 372,471.54 126,005.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,005.66