Dept. of Trans. PROGRESS Serial No. Contract No. 07-263-09-09 04-4R7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 57% 04-SM-1-21.5/29.0 Federal Project: NONE Progress payment No. 05 Payment period ending: 09-20-07 PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 02296 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,124,468.62 65,565.00 2.a. Extra Work 982.14 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,125,450.76 65,565.00 5. Mobilization 218,500.00 0.00 6. Total Work Completed 1,343,950.76 7. Deductions 8. a.Contract Retentions -56,272.54 -3,278.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,287,678.22 62,286.75 10. Reduction Amt to Escrow 11. Payment to Escrow 56,270.00 12. Net Pymt. this Estimate 62,286.75