Dept. of Trans. PROGRESS Serial No. Contract No. 15-141-15-59 04-4S0504 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 23% Location: Federal Project: 04-SCL-9-4.2 STP-S009(18) Progress payment No. 003 Payment period ending: 05-20-15 RGW CONSTRUCTION, INC. 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 486,153.20 355,228.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 87,206.00 87,206.00 4. Earned Subject to Retention 573,359.20 442,434.20 5. Mobilization 145,350.00 68,850.00 6. Total Work Completed 631,503.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 718,709.20 511,284.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 511,284.20