Dept. of Trans. PROGRESS Serial No. Contract No. 14-199-12-52 04-4S1604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 36% 04-SON-1-21.7/ .0 Federal Project: CSTP-P001(579) Progress payment No. 08 Payment period ending: 07-20-14 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 435,358.00 222.00 2.a. Extra Work 31,714.75 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 467,072.75 222.00 5. Mobilization 50,000.00 0.00 6. Total Work Completed 517,072.75 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 517,072.75 10,222.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,222.00