Dept. of Trans. PROGRESS Serial No. Contract No. 15-355-11-31 04-4S2204 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 5% Location: Federal Project: 04-MRN-1-10.9 STP-P001(589) Progress payment No. 002 Payment period ending: 12-20-15 GHILOTTI CONSTRUCTION CO. INC. 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,926.25 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 69,007.18 69,007.18 4. Earned Subject to Retention 78,933.43 69,007.18 5. Mobilization 59,500.00 59,500.00 6. Total Work Completed 69,426.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 138,433.43 128,507.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 128,507.18