Dept. of Trans. PROGRESS Serial No. Contract No. 16-168-09-49 04-4S2204 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 4% Location: Federal Project: 04-MRN-1-10.9 STP-P001(589) Progress payment No. 005 Payment period ending: 06-20-16 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 781,982.15 264,563.40 2. a. Extra Work 11,352.97 8,561.97 b. Adustment Comp. 3. Materials on Hand 3,559.25 3,559.25 4. Earned Subject to Retention 796,894.37 276,684.62 5. Mobilization 113,050.00 0.00 6. Total Work Completed 906,385.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 909,944.37 276,684.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,684.62