Dept. of Trans. PROGRESS Serial No. Contract No. 11-236-12-58 04-4S5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 15% 04-MRN-1-15.0/17.0 Federal Project: ACST-PP00(155) Progress payment No. 01 Payment period ending: 08-20-11 GHILOTTI BROTHERS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 94,373.33 94,373.33 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 94,373.33 94,373.33 5. Mobilization 79,000.00 79,000.00 6. Total Work Completed 173,373.33 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 173,373.33 173,373.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,373.33