Dept. of Trans. PROGRESS Serial No. Contract No. 12-145-12-21 04-4S6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 13% 04-SON-101-52.1/52.5 Federal Project: NHQ1-121(2E) Progress payment No. 03 Payment period ending: 05-20-12 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 74,800.00 74,800.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 383,935.62 0.00 4. Earned Subject to Retention 458,735.62 74,800.00 5. Mobilization 133,000.00 0.00 6. Total Work Completed 207,800.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 591,735.62 74,800.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,800.00