Dept. of Trans. PROGRESS Serial No. Contract No. 12-167-13-53 04-4S6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 25% 04-SON-101-52.1/52.5 Federal Project: NHQ1-121(2E) Progress payment No. 04 Payment period ending: 06-20-12 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 403,382.00 328,582.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 323,432.53 -60,503.09 4. Earned Subject to Retention 726,814.53 268,078.91 5. Mobilization 140,000.00 7,000.00 6. Total Work Completed 543,382.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 866,814.53 275,078.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,078.91