Dept. of Trans. PROGRESS Serial No. Contract No. 17-334-10-34 04-4S6604 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 47% Location: Federal Project: 04-MRN-1-8.1 NH Progress payment No. 001 Payment period ending: 10-27-17 THOMPSON BUILDERS CORPORATION 250 BEL MARIN KEYS BLVD BLDG NOVATO CA 94949 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 140,018.69 140,018.69 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 140,018.69 140,018.69 5. Mobilization 6. Total Work Completed 140,018.69 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 140,018.69 140,018.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,018.69