Dept. of Trans. PROGRESS Serial No. Contract No. 18-169-10-41 04-4S7804 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 20% Location: Federal Project: 04-MRN-1-24.7 ACST-P001(633) Progress payment No. 001 Payment period ending: 06-20-18 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 207,702.30 207,702.30 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 207,702.30 207,702.30 5. Mobilization 125,000.00 125,000.00 6. Total Work Completed 332,702.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 332,702.30 332,702.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 332,702.30