Dept. of Trans. PROGRESS Serial No. Contract No. 22-153-10-38 04-4W0104 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 100% Location: Federal Project: 04-SF-80-5.9/R7.6 NONE Progress payment No. 006 Payment period ending: 06-02-22 THE DUTRA GROUP 2350 KERNER BLVD #200 SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 920,313.87 174,007.56 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 920,313.87 174,007.56 5. Mobilization 6. Total Work Completed 920,313.87 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 920,313.87 174,007.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 174,007.56