Dept. of Trans. PROGRESS Serial No. Contract No. 22-147-09-48 04-4W7504 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 100% Location: Federal Project: 04-NAP-80-7.3/7.3 NONE 04-SOL-80-9.5/9.5 Progress payment No. 004 Payment period ending: 05-18-22 REDGWICK CONSTRUCTION CO. 21 HEGENBERGER CT OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 436,801.93 105,435.21 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 436,801.93 105,435.21 5. Mobilization 6. Total Work Completed 436,801.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 436,801.93 105,435.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,435.21