Dept. of Trans. PROGRESS Serial No. Contract No. 22-350-10-39 04-4W9504 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 73% Location: Federal Project: 04-SF-80-0.0/7.8 NONE 04-ALA-80-0.0/7.4 Progress payment No. 009 Payment period ending: 12-15-22 PERRY ELECTRIC INCORPORATED 130 MURWOOD CT WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 711,525.07 61,105.73 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 711,525.07 61,105.73 5. Mobilization 6. Total Work Completed 711,525.07 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 711,525.07 61,105.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,105.73