Dept. of Trans. PROGRESS Serial No. Contract No. 26-005-10-34 04-4X0204 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 0% Location: Federal Project: 04-SCL-880-1.7/1.9 NONE Progress payment No. 003 Payment period ending: 12-31-25 ABSL CONSTRUCTION 29393 PACIFIC ST HAYWARD CA 94544-6018 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 307,536.80 36,004.28 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 307,536.80 36,004.28 5. Mobilization 6. Total Work Completed 307,536.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 307,536.80 36,004.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,004.28