Dept. of Trans. PROGRESS Serial No. Contract No. 25-350-13-53 04-4X3804 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 4% Location: Federal Project: 04-CC-80-7.6/7.6 NONE Progress payment No. 001 Payment period ending: 12-20-25 GOLDEN STATE BRIDGE, INC. 3701 MALLARD DRIVE BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 194,409.73 194,409.73 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 194,409.73 194,409.73 5. Mobilization 6. Total Work Completed 194,409.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 194,409.73 194,409.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 194,409.73