Dept. of Trans. PROGRESS Serial No. Contract No. 26-082-15-21 04-4X4504 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 23% Location: Federal Project: 04-SM-1-R47.6/R47.6 NONE Progress payment No. 002 Payment period ending: 02-28-26 SANTAMARIA CONCRETE, INC. 785 LINCOLN AVE. SAN JOSE, CA 95126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 159,341.19 116,149.82 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 159,341.19 116,149.82 5. Mobilization 6. Total Work Completed 159,341.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 159,341.19 116,149.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,149.82