Dept. of Trans. PROGRESS Serial No. Contract No. 23-289-08-53 04-4Y0204 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 44% Location: Federal Project: 04-SM-84-13.8/13.8 NONE Progress payment No. 001 Payment period ending: 08-26-23 REDWOOD ENGINEERING CONSTRUCTION 416 D ST REDWOOD CITY CA 94063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 242,653.00 242,653.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 242,653.00 242,653.00 5. Mobilization 6. Total Work Completed 242,653.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 242,653.00 242,653.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 242,653.00