Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-14-54 04-4Y0804 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 73% Location: Federal Project: 04-SM-1-36.9/36.9 NONE Progress payment No. 001 Payment period ending: 09-16-24 YERBA BUENA ENGINEERING AND CONSTRUCTION INC 1340 EGBERT AVENUE SAN FRANCISCO CA 94124 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 468,875.84 468,875.84 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 468,875.84 468,875.84 5. Mobilization 6. Total Work Completed 468,875.84 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 468,875.84 468,875.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 468,875.84