Dept. of Trans. PROGRESS Serial No. Contract No. 00-297-14-54 05-016174 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 14% 05-MON-101-96.1/ .0 Federal Project: ACNH-P101(930) Progress payment No. 03 Payment period ending: 10-20-00 PAVEX CONSTRUCTION DIVISION 330 BLOMQUIST STREET REDWOOD CITY CA 94063 Escrow No. 01481 Total Estimate This Estimate 1. Contract Itms Without Mobil. 388,914.50 286,804.52 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 388,914.50 286,804.52 5. Mobilization 300,000.00 300,000.00 6. Total Work Completed 688,914.50 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -38,891.45 -28,680.45 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 640,023.05 548,124.07 10. Reduction Amt to Escrow 11. Payment to Escrow 38,890.00 12. Net Pymt. this Estimate 548,124.07