Dept. of Trans. PROGRESS Serial No. Contract No. 12-170-08-27 05-0161E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 33% 05-MON-101-R91.2/100.4 Federal Project: NH-Q101(187) Progress payment No. 16 Payment period ending: 06-20-12 GCC/MCM A JV P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,437,335.13 2,090,433.87 2.a. Extra Work 1,424,584.25 138,272.06 b. Adjustment Comp. 267,674.77 0.00 3. Materials on Hand 823,403.28 248,047.78 4. Earned Subject to Retention 26,952,997.43 2,476,753.71 5. Mobilization 4,060,030.20 0.00 6. Total Work Completed 30,189,624.35 7. Deductions -30,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,983,027.63 2,486,753.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,486,753.71