Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-205-14-04 05-0161E4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-MON-101-R91.2/100.4 NH-Q101(187) Progress payment No. 052 Payment period ending: 04-14-15 GCC/MCM A JV P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 68,430,482.86 11,170.00 2. a. Extra Work 10,557,904.28 0.00 b. Adustment Comp. 2,114,834.79 249,244.58 3. Materials on Hand 4. Earned Subject to Retention 81,103,221.93 260,414.58 5. Mobilization 4,273,716.00 0.00 6. Total Work Completed 85,376,937.93 7. Deductions -12,232.25 117,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 85,364,705.68 377,914.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 377,914.58