Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 02-283-10-45 05-0161U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 47% 05-MON-101-95.0/95.8 Federal Project: ACNH-X053(20) Progress payment No. 11 Payment period ending: 09-20-02 R M HARRIS COMPANY INC 1000 HOWE ROAD, STE 200 MARTINEZ CA 94553 Escrow No. 01863 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,072,878.71 0.00 2.a. Extra Work 7,084.28 0.00 b. Adjustment Comp. 3. Materials on Hand 141,998.88 0.00 4. Earned Subject to Retention 2,221,961.87 0.00 5. Mobilization 684,000.00 0.00 6. Total Work Completed 2,763,962.99 7. Deductions -31,345.38 70,242.92 8. a.Contract Retentions -135,511.49 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,739,105.00 70,242.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,242.92