Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 04-342-08-56 05-0161U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 05-MON-101-95.0/95.8 Federal Project: ACNH-X053(20) Progress payment No. 40 Payment period ending: 11-20-04 R M HARRIS COMPANY INC 1000 HOWE ROAD, STE 200 MARTINEZ CA 94553 Escrow No. 01863 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,037,559.73 -127,304.30 2.a. Extra Work 1,182,588.07 134,885.07 b. Adjustment Comp. 1,130.88 0.00 3. Materials on Hand 4,328.92 -1,795.31 4. Earned Subject to Retention 7,225,607.60 5,785.46 5. Mobilization 720,000.00 0.00 6. Total Work Completed 7,941,278.68 7. Deductions -54,832.57 0.00 8. a.Contract Retentions -361,280.38 -289.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 37,949.32 37,949.32 9. Total pay to Contractor 7,567,443.97 43,445.51 10. Reduction Amt to Escrow 11. Payment to Escrow 142,694.00 12. Net Pymt. this Estimate 43,445.51