Dept. of Trans. PROGRESS Serial No. Contract No. 19-109-10-10 05-0A0504 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 11% Location: Federal Project: 05-SB-1-15.6 B1NH-P001(641) Progress payment No. 003 Payment period ending: 04-20-19 CALPORTLAND CONSTRUCTION PO BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 551,954.05 242,699.55 2. a. Extra Work 19,361.88 9,985.12 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 571,315.93 252,684.67 5. Mobilization 393,750.00 131,250.00 6. Total Work Completed 965,065.93 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 965,065.93 385,934.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 385,934.67