Dept. of Trans. PROGRESS Serial No. Contract No. 19-203-15-12 05-0A0504 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 31% Location: Federal Project: 05-SB-1-15.6 B1NH-P001(641) Progress payment No. 006 Payment period ending: 07-20-19 CALPORTLAND CONSTRUCTION PO BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,251,530.14 245,604.61 2. a. Extra Work 47,989.64 1,950.99 b. Adustment Comp. 3. Materials on Hand 8,649.90 0.00 4. Earned Subject to Retention 1,308,169.68 247,555.60 5. Mobilization 498,750.00 0.00 6. Total Work Completed 1,798,269.78 7. Deductions -6,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,800,919.68 245,555.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 245,555.60