Dept. of Trans. PROGRESS Serial No. Contract No. 22-203-09-06 05-0A0904 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 25% Location: Federal Project: 05-MON-156-R1.4/R2.0 NONE Progress payment No. 004 Payment period ending: 07-20-22 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 938,312.77 285,753.06 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 938,312.77 285,753.06 5. Mobilization 420,000.00 0.00 6. Total Work Completed 1,358,312.77 7. Deductions -205.50 -205.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,358,107.27 285,547.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 285,547.56