Dept. of Trans. 95% REDUCTION Serial No. Contract No. 05-024-13-39 05-0A1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-101-41.3/46.9 Federal Project: ACST-Q101(51) PHG-Q101(51) Progress payment No. 12 Payment period ending: 01-20-05 WHITAKER CONTRACTORS INC P O BOX 910 SANTA MARGARITA CA 93453 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,387,347.19 450.00 2.a. Extra Work 78,452.33 0.00 b. Adjustment Comp. 28,124.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,493,923.57 450.00 5. Mobilization 35,000.00 0.00 6. Total Work Completed 2,528,923.57 7. Deductions 0.00 1,000.00 8. a.Contract Retentions -124,696.18 -22.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 107,415.22 585.00 9. Total pay to Contractor 2,511,642.61 2,012.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,012.50