Dept. of Trans. PROGRESS Serial No. Contract No. 04-170-08-02 05-0A2304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 34% 05-SLO-166-12.9/R70.1 Federal Project: 05-SB-166-22.9/R70.1 ACST-P166(23) PHG-P166(23) Progress payment No. 02 Payment period ending: 06-20-04 C AND W CONSTRUCTION SPECIALTIES INC 2419 PALMA DRIVE VENTURA CA 93003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 97,896.66 95,586.66 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 97,896.66 95,586.66 5. Mobilization 34,958.50 34,958.50 6. Total Work Completed 132,855.16 7. Deductions -4,365.27 -4,365.27 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 128,489.89 126,179.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,179.89