Dept. of Trans. PROGRESS Serial No. Contract No. 09-328-14-53 05-0A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 82% 05-SLO-227-R10.9/R14.2 Federal Project: ACNH-S227(5) Progress payment No. 15 Payment period ending: 11-20-09 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,973,611.53 1,634,723.56 2.a. Extra Work 194,859.18 11,495.18 b. Adjustment Comp. -258,363.47 -258,363.47 3. Materials on Hand 7,249.46 0.00 4. Earned Subject to Retention 5,917,356.70 1,387,855.27 5. Mobilization 157,000.00 0.00 6. Total Work Completed 6,067,107.24 7. Deductions -2,653.75 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,071,702.95 1,387,855.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,387,855.27